Handover inspection: common defects and the NCC clauses behind them

Editions covered: NCC 2022 (current in most states), NCC 2025 (WA, VIC, ACT) · Last reviewed 15 November 2026

At practical completion, it's easy to focus on paint and scratches and miss the items that are actually NCC requirements. Many of those items are easiest to check before the keys change hands: safety glass labels, window restrictors, shower falls, smoke alarm interconnection and the termite notice. This guide lists the defects that come up most often at handover, with the NCC clause to point to for each. It also explains where state "standards and tolerances" guides fit in for finish quality.

Which edition?

  • NCC 2022 applies in NSW, QLD, SA, TAS and the NT.
  • NCC 2025 applies in WA, VIC and the ACT from 1 May 2026. WA and the ACT allow a 12-month transition.
  • The Housing Provisions clauses below read the same in both editions.

Where the rules are

  • NCC Volume Two and the ABCB Housing Provisions: these set the minimum technical requirements. They don't set finish quality, such as paint sheen, plaster flatness or tile lippage.
  • State standards and tolerances guides: these describe acceptable finish and workmanship for many items. They are guidance documents, used in disputes and for consumer information:
    • NSW: Guide to Standards and Tolerances 2017
    • QLD: QBCC Standards and Tolerances Guide
    • VIC: the Building and Plumbing Commission's Guide to Standards and Tolerances 2026.
  • Your contract and approved plans: these may set higher requirements than the NCC.

Key requirements: the handover checklist

Each item gives the NCC clause to cite. Check it against your plans and edition.

  1. Shower and wet-area floor falls (HP 10.2.12): where there is a floor waste, the floor must fall to it at between 1:80 and 1:50. Puddles that stay after a shower test are a common sign of a problem. See our wet-area waterproofing guide.

  2. Safety glass labels (HP 8.4.8): each piece of safety glass needs a permanent etch or a non-reusable label. The label shows the Standard, the maker, the grade, the thickness and the type. The NCC's notes say labels aren't meant to last beyond construction, but they should stay on long enough for practitioners to confirm and certify the glass. See our glazing guide.

  3. Bedroom window restrictors (HP 11.3.7): these are needed where the floor is 2 m or more above the ground and the opening is below 1.7 m.

    • The restrictor must stop a 125 mm sphere and resist a 250 N push.
    • If it can be released, the release must be child resistant, and an 865 mm barrier is also needed.
  4. Balustrades (HP 11.3.3 and 11.3.4): required where a fall is 1 m or more.

    • Height: at least 1 m on decks and balconies, and 865 mm along stairs.
    • Openings: no opening that would let a 125 mm sphere through.
    • See our balustrades and stairs guide.
  5. Smoke alarms (HP Part 9.5): smoke alarms must:

    • comply with AS 3786, and be mains powered where mains supply is available
    • be interconnected where there is more than one
    • be on every storey, in the hallway or area outside the bedrooms.

    Press-test them at handover. See our smoke alarms guide for state rules.

  6. Slab height and ground falls (HP 3.3.3 and 7.5.7):

    • The slab must sit 150 mm above the finished ground, or 100 mm or 50 mm in the cases the NCC allows.
    • The ground must fall 50 mm over the first 1 m away from the house.
    • Late landscaping often breaks these. See our site drainage guide.
  7. Weep holes (HP 5.7.5): brick veneer needs open weep joints in the course directly above flashings and the damp-proof course.

    • They must be at least 50 mm high and no more than 1.2 m apart.
    • They aren't needed under sills or above openings less than 1.2 m wide.
    • Check that they haven't been rendered over or blocked by paving. See our brickwork guide.
  8. Termite notice (HP 3.4.3): a durable notice must be fixed in a prominent place, such as the meter box. It states:

    • the termite system used
    • the date it was installed
    • the chemical life, if a chemical is used
    • the recommended inspections.

    Check that inspection zones are visible and haven't been bridged. See our termite guide.

  9. Exhaust fans (HP 10.8.2, both editions):

    • Kitchen, bathroom, WC and laundry exhaust must discharge to outdoor air, not into the roof space.
    • A bathroom or WC fan that isn't run continuously, in a room without natural ventilation, must be interlocked with the light and have a 10-minute run-on.
    • Look for ducting that ends inside the roof space. See our condensation guide.
  10. Insulation (HP 13.2.2): lift a manhole and check:

    • batts are continuous and butted together, not compressed
    • insulation doesn't interfere with the safe operation of downlights, flues and other services
    • batts are reinstated after electricians and plumbers have finished.

    See our energy guide.

  11. Door seals (HP 13.4.4): in climate zones 4 to 8, or in conditioned spaces, external doors need a draught device at the bottom and seals on the other edges.

How the states differ

  • NSW: the Guide to Standards and Tolerances 2017 (NSW Government, Building Commission NSW) explains acceptable finish standards for common items. NSW uses BASIX for energy, so check the BASIX certificate commitments at handover, such as the hot water system, fixtures, insulation and any tank.
  • Queensland: the QBCC Standards and Tolerances Guide (December 2023 edition) sets out acceptable tolerances. Its foreword says it draws on the NCC, referenced Standards and manufacturers' instructions.
  • Victoria: the Building and Plumbing Commission's Guide to Standards and Tolerances 2026 applies to domestic building contracts entered into, or work started, on or after 1 August 2026. Earlier jobs use the previous edition. The BPC says the guide is a benchmark for workmanship and doesn't replace legislation, the NCC or the contract.
  • WA, SA, TAS, ACT and NT: check with the state building regulator for consumer guidance on defects and the dispute process. The NCC clauses above apply nationally.
  • Statutory warranties and defect periods are set by state home building laws and vary. We don't list them here. Check your contract and the state regulator.

Ask the app

Upload up to four photos of the item you're unsure about, such as a shower floor, a glass label, a window or a weep hole, or ask:

  • "Is this shower fall enough?"
  • "Does this window need a restrictor? The bedroom is upstairs."
  • "The landscaper paved up to the weep holes. Is that a defect?"
  • "Do the smoke alarms in this house need to be interconnected?"
  • "Where should the termite notice be?"

Ask a builder question · Waterproofing · Glazing · Fire · General

Related checklists

FAQ

What should I check at a practical completion inspection? Beyond finishes, check the items the NCC requires: shower falls, safety glass labels, window restrictors, balustrade heights and gaps, interconnected smoke alarms, slab height and ground falls, clear weep holes, the termite notice, exhaust fans ducted outside, and insulation and seals.

Is a hairline crack in plaster or a slab an NCC defect? The NCC doesn't set finish tolerances. The state standards and tolerances guides, such as those from NSW and the QBCC, describe what is generally acceptable. Your builder, certifier or the state regulator can advise on a particular case.

Should the safety glass stickers be left on? The NCC's explanatory note says labels are not intended to remain after completion. They should stay in place long enough for the work to be checked and certified (HP 8.4.8). Ask your builder before removing them.

Does the NCC say how much fall a shower floor needs? Yes. Where a floor waste is installed, the fall to the waste must be between 1:80 and 1:50 (HP 10.2.12).

Who do I contact about defects after handover? Start with your builder, under the contract. If that doesn't resolve it, contact your state building regulator. Statutory warranty periods and dispute processes differ by state.


This is general guidance, not a compliance check. Always check your approved plans, your contract and the edition that applies to your permit, and confirm details with your certifier or building surveyor.

Based on content from the National Construction Code 2022 and 2025 (NCC Volume Two and the ABCB Housing Provisions), provided by the Australian Building Codes Board under the CC BY 4.0 licence. The ABCB does not endorse this guide. The standards the NCC references are cited and explained in our own words, not reproduced.

Sources

  • ABCB Housing Provisions Standard 2022 (1 May 2023): 3.3.3, 3.4.3, 5.7.5, 7.5.7, 8.4.8, 9.5.1, 9.5.2, 10.2.12, 10.8.2, 11.3.3, 11.3.4, 11.3.7, 13.2.2, 13.4.4
  • ABCB Housing Provisions Standard 2025: the same clauses were compared and no change was found. 10.8.2 keeps the same number and these requirements
  • NSW Government, Guide to Standards and Tolerances: https://www.nsw.gov.au/housing-and-construction/building-or-renovating-a-home/after/safety-and-standards/guide-standards-and-tolerances
  • Building and Plumbing Commission (Vic), Guide to Standards and Tolerances 2026: https://www.bpc.vic.gov.au/resource-hub/guides/guide-to-standards-and-tolerances-2026
  • QBCC, Standards and Tolerances Guide (December 2023): https://qbcc.qld.gov.au/sites/default/files/documents/guide-standards-tolerances.pdf
  • ABCB, NCC 2025 adoption dates: https://ncc.abcb.gov.au/ncc-2025/ncc-2025-state-and-territory-adoption-information
  • Standards cited by number only: AS 3786