Slabs and footings: what the NCC asks for

Editions covered: NCC 2022 (current in most states), NCC 2025 (WA, VIC, ACT) · Last reviewed 15 November 2026

Once the concrete is poured, nobody can see what's under it. A torn underlay, poorly compacted fill, low reinforcement chairs or a missing re-entrant bar can't be fixed later. That's why the pre-pour inspection matters so much. This guide explains when the NCC lets a house slab be built to the simplified Housing Provisions, and when it must be engineered to AS 2870. It also covers the details checked before the pour.

Which edition?

  • NCC 2022 applies in NSW, QLD, SA, TAS and the NT.
  • NCC 2025 applies in WA, VIC and the ACT from 1 May 2026. WA and the ACT allow a 12-month transition.
  • The clauses quoted below from Housing Provisions Part 4.2 read the same in both editions.

Where the rules are

  • NCC Volume Two H1D4(1): footings and slabs comply with one of:
    • AS 2870 (residential slabs and footings)
    • AS 3600 (concrete structures)
    • ABCB Housing Provisions Section 4 (Part 4.2).
  • H1D4(2): the limits on using the Housing Provisions route.
  • H2D3: footings and slabs for damp and weatherproofing.
  • AS 2870 (2011 edition referenced) and AS 3600 are cited by number only.

Key requirements

  1. When you can use the Housing Provisions (H1D4(2)): the HP route is limited to:

    • Class A, S or M sites with uniform bearing
    • slabs no more than 18 m long or wide, with only external right angles and no more than one re-entrant corner
    • no permanent joints, and one slab per footing
    • no aggressive soils
    • no more than two trafficable floors, and walls no more than 8 m high (excluding gables)
    • a "normal" site (HP Part 3.2), outside alpine areas, with no specific earthquake design requirements.

    Anything outside these limits, including H, E and P sites, follows AS 2870 or an engineer's design. Check the drawings to see which route your slab design uses.

  2. Site classification (HP 4.2.2): the site must be classified under AS 2870. The explanatory table gives a general guide:

    • A: sand and rock, little movement
    • S: slightly reactive clay
    • M: moderately reactive
    • H: highly reactive
    • E: extremely reactive
    • P: problem sites, such as soft soils, uncontrolled fill, trees or erosion.
  3. Excavation (HP 4.2.3):

    • Trenches are clean cut.
    • The base is level within 1:40 on flat sites, and no steeper than 1:10 on sloping sites.
    • Trenches are free of loose earth, roots and mud, with topsoil removed.
    • On loose sand or erosion-prone sites, footings are at least 300 mm below finished ground.
  4. Fill under slabs (HP 4.2.4):

    • Controlled fill:
      • sand up to 800 mm deep, compacted in layers of no more than 300 mm
      • clay up to 400 mm, in layers of no more than 150 mm.
    • Rolled fill:
      • sand up to 600 mm
      • clay up to 300 mm.
    • Sand blinding: at least 20 mm of clean quarry sand goes on top. A graded stone termite system can replace it.
  5. Bearing (HP 4.2.5):

    • Slab panels and connected edge beams sit on natural soil of at least 50 kPa, or on fill compacted as above.
    • Pad and strip footings, and edge beams not connected to the slab, need at least 100 kPa natural soil. On A and S sites, controlled sand fill is also accepted.
  6. Vapour barrier (HP 4.2.8): under every Class 1 slab-on-ground, and any garage slab continuous with it.

    • Material: 0.2 mm polyethylene, medium impact resistance, continuously branded as AS 2870 concrete underlay.
    • Installation:
      • lapped at least 200 mm
      • taped or sleeved at penetrations, with punctures patched
      • running under all beams to finish at ground level.
  7. Edge rebates (HP 4.2.9): for masonry veneer or cavity walls, the rebate is at least 20 mm, and is flashed and drained or filled with mortar.

  8. Concrete (HP 4.2.10):

    • N20 strength, 20 mm maximum aggregate and nominal 100 mm slump.
    • No water added on site to raise the slump.
    • Placed, compacted and cured to good practice.
  9. Reinforcement (HP 4.2.11):

    • Re-entrant corners need extra steel: two strips of 3-L8TM, one of 3-L11TM, or 3-N12 bars.
    • Concrete cover must be at least:
      • 40 mm to unprotected ground
      • 30 mm to a membrane
      • 20 mm internally
      • 40 mm to external exposure.
    • Chairs sit on flat bases on soft ground or membrane, and are spaced no more than 800 mm apart for fabric.
  10. Tiles and other brittle floors (HP 4.2.19): where brittle coverings such as ceramic tiles cover more than 16 m², do one of these:

    • upgrade the mesh to SL92, or use top and bottom mesh
    • choose a bedding system that suits the expected slab movement
    • wait at least 3 months after the pour before laying.
  11. Edge beams and recesses (HP 4.2.21 and 4.2.22):

    • Edge beams: at least 200 mm wide at the rebate base, or 150 mm with R10/N10 ties at 900 mm.
    • Recesses (for example, set-down showers): mesh laps at least 400 mm from the inside face of the recess. Deeper recesses need top-to-bottom mesh overlap and two layers of SL72.

How the states differ

  • NSW: NSW H1D4(1) and NSW 4.2.8 replace the vapour barrier with a high impact resistance damp-proofing membrane, branded as such. This applies on the AS 2870 route too. NSW H2P3 explains why: better puncture resistance against salt-laden moisture. The NSW 4.2.3 note says shoring and excavation adequacy are prescribed conditions of development consent.
  • South Australia:
    • SA 4.2.8 also requires a high impact damp-proofing membrane, branded with the maker's name.
    • SA 4.2.10 adds:
      • 7 days of moist curing, with slab edges finished before curing
      • no stacked materials or plant on the slab for 7 days
      • no pouring above 32 °C without written instructions from a professional engineer.
  • WA, VIC, QLD, TAS, ACT and NT: no variation to these Housing Provisions clauses.

Ask the app

Upload a photo of the underlay laps, bar chairs or re-entrant corner bars before the pour, or ask:

  • "What lap does the slab vapour barrier need?"
  • "Can the Housing Provisions be used on a class H site?"
  • "How much concrete cover is needed over mesh on a membrane?"
  • "Do I need extra mesh under a large tiled floor?"
  • "Does NSW need a high impact membrane under the slab?"

Ask a concreting question · Structural · Earthworks · Builder

Related checklists

FAQ

What do site classes A, S, M, H, E and P mean? They describe how much the foundation is expected to move with moisture changes. A is stable sand or rock, S, M, H and E are increasingly reactive clays, and P covers problem sites. The class is set under AS 2870 (HP 4.2.2).

When does a slab have to be engineered? When it falls outside the H1D4(2) limits. Examples are H, E or P sites, slabs over 18 m, more than one re-entrant corner, more than two storeys, or aggressive soils. Your drawings show which route the design uses.

What vapour barrier goes under a slab? Nationally, 0.2 mm polyethylene with medium impact resistance, branded as AS 2870 concrete underlay, lapped 200 mm and sealed at penetrations. NSW and SA require the high impact grade (HP 4.2.8, NSW 4.2.8, SA 4.2.8).

How much concrete cover do I need over reinforcement? 40 mm to unprotected ground, 30 mm to a membrane, 20 mm internally and 40 mm to external exposure (HP 4.2.11(5)).

Can tiles be laid straight onto a new slab? For brittle floors over 16 m², the NCC requires one of these: heavier or double mesh, a bedding system designed for the slab movement, or a 3-month wait after the pour (HP 4.2.19).

Can water be added to concrete on site? Not to raise the slump above the specified 100 mm (HP 4.2.10(b)).


This is general guidance, not a compliance check. Always check your approved plans and the engineer's slab design, and the edition that applies to your permit, and confirm details with your certifier or building surveyor.

Based on content from the National Construction Code 2022 and 2025 (NCC Volume Two and the ABCB Housing Provisions), provided by the Australian Building Codes Board under the CC BY 4.0 licence. The ABCB does not endorse this guide. The standards the NCC references are cited and explained in our own words, not reproduced.

Sources

  • NCC 2022 Volume Two: H1D4 (including NSW H1D4(1)), NSW H2P3, H2D3
  • ABCB Housing Provisions Standard 2022 (1 May 2023): 4.2.2 to 4.2.5, 4.2.8 to 4.2.11, 4.2.19, 4.2.21, 4.2.22, NSW 4.2.3, NSW 4.2.8, SA 4.2.8, SA 4.2.10
  • ABCB Housing Provisions Standard 2025: the same clauses (including the NSW and SA variations) were compared and no change was found
  • NCC 2025 Volume Two, Part H1 (H1D4): https://ncc.abcb.gov.au/editions/ncc-2025/adopted/volume-two/h-class-1-and-10-buildings/part-h1-structure
  • ABCB, NCC 2025 adoption dates: https://ncc.abcb.gov.au/ncc-2025/ncc-2025-state-and-territory-adoption-information
  • Standards cited by number only: AS 2870:2011, AS 3600